Brick Machine Mold Replacement Procedure

2025-11-05

A: 1. Clean the mold thoroughly.


2. Place a shim block at the position of the demolding baffle corresponding to the press head on the mold frame. The height of the shim block should ensure that the press plate does not protrude from the mold frame when the press head is placed on it.


3. Slowly lower the press head, ensuring it is placed in the mold frame. Once the press head reliably contacts the mold frame, separate the press head from the main unit. The main unit's press head will then rise to its final position.


4. As the mold frame rises, if a quick-change mold device is present, it will engage at this point. The mold frame will then descend onto the quick-change device, and the mold frame's air bladder will lift to its final position.


The quick-change mold device will then retract to its final position. If a main unit cantilever crane is used, use the cantilever crane to lift the mold out. Then, transfer it to the mold placement rack using a forklift.


5. If there is no quick mold changing device, a pallet needs to be placed under the vibrating table and at the brick receiving machine. Then, a jack or steel pipe should be placed under the mold frame to lower the mold frame into place. The mold should be transferred from the main machine using the jack or steel pipe. After reaching the brick receiving machine, a forklift should be used to lift the mold down and then transfer it to the mold placement rack using a forklift.